Microsoft Dynamics 365 Supply Chain Management, Manufacturing MB-320 training questions have been updated, which are valuable for you to clear the test. Candidates for this Microsoft MB-320 exam typically specialize in one or more feature sets of Microsoft Dynamics 365 Finance, including finance, manufacturing, and supply chain management.

 

MB-320 Exam Associated Certification

Microsoft MB-320 exam is a required test for Microsoft Certified: Dynamics 365 Supply Chain Management, Manufacturing Functional Consultant Associate certification, which also requires you to pass MB-300 exam. 

Microsoft MB-320 Exam Topics

Microsoft certification MB-320 exam topics cover the following sections.
Set up and configure manufacturing (30-35%)
Create and manage production and lean orders (25-30%)
Create, process, and manage production batch orders (40-45%)

New Updated MB-320 Training Questions

The new updated Microsoft MB-320 training questions can help you test the above topics. Share some Microsoft Dynamics 365 Supply Chain Management, Manufacturing MB-320 exam updated training questions below. 
1.You need to set up the state control for sales of motorcycles. Which two actions should you perform? Each correct answer presents part of the solution. NOTE: Each correct selection is worth one point.
A. Create an inclusive restricted product list for United States. Do not add the motorcycle part to the list.
B. Create an inclusive restricted product list for United States and add the motorcycle part to the list.
C. Create an exclusive restricted product list for California and add the motorcycle part to the list.
D. Create an exclusive restricted product list for Missouri and add the motorcycle part to the list.
Answer: BC

2.A beverage company uses Dynamics 365 Supply Chain Management batch processing for production. You need to identify the ingredient type used in batch processing when the base attribute of a product is added to a formula line. What is the ingredient type?
A. filler
B. active
C. compensating
D. none
Answer: B

3.You are the lead product design manager at a Process manufacturing plant. You are building a formula that produces egg yolks as a by-product. This by-product is added back into inventory at standard cost and can be used in other production batches. You need to select the by-product cost allocation. Which cost allocation type should you use?
A. Per series
B. Per quantity
C. Recycled
D. Percent
Answer: C

4.You are the production scheduler at a manufacturing company. The company is not using advanced warehousing. You have firmed a planned production order from master planning. The order is ready to be processed. You now need to process the order in production control. What should you do first?
A. Report the order as finished
B. Estimate the order
C. Schedule the order
D. Start the order
Answer: B

5.You have updated a cost category price from $5.00 to $7.00. You process a production order which uses the cost category. After ending the order, you realize a new standard cost was not calculated after the price update. You need to validate how this impacted the financial voucher transactions. Which transaction would you see in the general ledger?
A. $2.00 debit to the production price variance account
B. $2.00 credit to the production price variance account
C. $2.00 debit to the production quantity variance account
D. $2.00 credit to the lot size variance account
Answer: B